Topic Title: Scheduled task wont start Topic Summary: Created On: 08/29/2017 08:17 AM Status: Read Only |
Linear : Threading : Single : Branch |
![]() |
![]()
|
![]() |
||||||||||
Hi, Few times we had issue where scheduled task wont start on schduled time. It ran previously but stopped without any reason. Can someone let me know what it can be? Thanks!
|
||||||||||
|
||||||||||
![]() |
||||||||||
Hello,
Were there any errors given in the Task Administrator or Event Viewer (under application)? If so can you provide them. What types of tasks are you running (interactive or background type)?
------------------------- ![]() Ricardo Castaneda | Principal Support Analyst AutoMate | Division of HelpSystems HelpSystems, LLC | T: +1.213.738.1700 |
||||||||||
|
||||||||||
![]() |
||||||||||
I dont know at this point. WHere i can check on that? Thanks!
|
||||||||||
|
||||||||||
![]() |
||||||||||
Hi, The errors in Task Administrator would be in the "Logs" section. Event Viewer can be found in Windows. Finding out if the task is interactive or background can be found in Automate. Right-click the task, go to Properties > Logon. Is the task set to run as a logged in user or in the background?
------------------------- ![]() Devin Cannon | Support Analyst AutoMate | Division of HelpSystems HelpSystems, LLC | T: +1.213.738.1700 | F: +1.213.738.7665 |
||||||||||
|
||||||||||
![]() |
||||||||||
Task is running as logged in user.
|
||||||||||
|
||||||||||
![]() |
||||||||||
Hi NeshoDostic,
When the task fails to run on it's schedule, is the next scheduled date updating? Also, what is the tasks Rescheduling set to? This is found by editing the scheduled trigger.
------------------------- ![]() Justin Aucoin | Support Analyst AutoMate | Division of HelpSystems HelpSystems, LLC | T: +1.213.738.1700 | F: +1.213.738.7665 |
||||||||||
|
||||||||||
![]() |
||||||||||
When the task fails to run on it's schedule, is the next scheduled date updating? I didnt see that. Also, what is the tasks Rescheduling set to? I attached image with options selected under rescheduling. Thanks!
|
||||||||||
|
||||||||||
![]() |
||||||||||
Hi NeshoDostic,
The most likely cause of the issue is that there is a delay in starting the task at the scheduled time. With your current 'When the trigger is late' setting of 'Ignore & Reschedule', any delay in starting the task will result in it being skipped and running on it's next schedule. The causes for the delays can include the system being off, or high usage on the system delaying the triggering. Please try setting the task instead to 'Run it immediately'. This should resolve the issue.
------------------------- ![]() Justin Aucoin | Support Analyst AutoMate | Division of HelpSystems HelpSystems, LLC | T: +1.213.738.1700 | F: +1.213.738.7665 |
||||||||||
|
||||||||||
![]() |
||||||||||
Will do it. Thank you for your help!
|
||||||||||
|